Offshore Facility HAZOP Mitigation

Upstream

Location

Nameplate Capacity

Keystone led efforts to mitigate findings from HAZOP reviews.  Keystone assisted at5 different locations and the review scope ranged from 10 to 90 items.  Keystone was able to mitigate 65% of these findings without facility modifications, using additional analysis tools and process modelling.  If modifications were necessary, Keystone worked to minimize the field scope for most to a coding change or addition of a monitoring point.  For larger multi-discipline items, Keystone handled the design effort and coordinated installation with existing turnaround planning efforts.

To learn more about our Renewable Energy department,
please click to visit our Renewables site.